Timeline

Gantt Chart:

Gantt Chart Aperture Biosystems Lab

Important Dates:

10/28/14: Obtain an initial scenario flowchart from sponsor

11/4/14: Observe a simulation session and finish website

11/5/14: Choose/purchase a platform for game development

11/17/14: Begin translating initial flowchart into appropriate programming language

12/2/14: Functional product with one finished scenario

1/10/15: Obtain second scenario flowchart from sponsor

3/1/15: Finish programming second scenario

3/10/15: Obtain third scenario flowchart from sponsor

4/2/15: Finish programming third scenario

4/15/15: Finish fine tuning aesthetics of the virtual interface

4/20/15: Present project at Design Day